(see clause 3.10.5(1 & 2), 3.10.8(1), 3.15.3, 14.2, 14.4.2, 14.4.3, 14.4.4)
TIMELINES FOR DIFFERENT ACTIVITIES FOR ISSUING BUILDING LICENCE, NOCS AND CERTIFICATION OF WORKS EXECUTED AT SITE AS PER THE CONDITIONS OF NOC, BY DIFFERENT DEPARTMENTS, FOR DIFFERENT TYPES OF BUILDING.
Timeline for issuing NOCs
The timelines for issuing various NOCs mentioned in these byelaws shall be as notified by the Government.
Timeline for issuing building licence
| Sl.No | Description of Standard Activities | Description of Additional Activities | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) |
| Sl.No | Description of Standard Activities | Description of Additional Activities | ** | B1 | B1 | B1 | B2 | B2 | B2 | B3 | B3 | B3 | B4 | B4 | B4 | B5 | B5 | B5 |
| Sl.No | Description of Standard Activities | Description of Additional Activities | ** | a* | b* | c* | a* | b* | c* | a* | b* | c* | a* | b* | c* | a* | b* | c* |
| Activities for all types of Approval of Plot | Activities for all types of Approval of Plot | Activities for all types of Approval of Plot | Activities for all types of Approval of Plot | Activities for all types of Approval of Plot | Activities for all types of Approval of Plot | Activities for all types of Approval of Plot | Activities for all types of Approval of Plot | Activities for all types of Approval of Plot | Activities for all types of Approval of Plot | Activities for all types of Approval of Plot | Activities for all types of Approval of Plot | Activities for all types of Approval of Plot | Activities for all types of Approval of Plot | Activities for all types of Approval of Plot | Activities for all types of Approval of Plot | Activities for all types of Approval of Plot | Activities for all types of Approval of Plot | |
| 1 | The CEO of the Authority to verify the documents submitted along with the application. | A | 1 | 1 | 1 | 1 | 1 | 1 | 2 | 2 | 2 | 3 | 3 | 3 | 3 | 3 | 3 | |
| 1 | The CEO of the Authority to verify the documents submitted along with the application. | C | 1 | 1 | 1 | 1 | 1 | 1 | 2 | 2 | 2 | 3 | 3 | 3 | 3 | 3 | 3 | |
| 2 | Issuing endorsement in case of discrepancy | A | 1 | 1 | 1 | 1 | 1 | 1 | 2 | 2 | 2 | 3 | 3 | 3 | 3 | 3 | 3 | |
| 3 | Applicant to rectify the defects and resubmit the documents and acceptance of the same by the designated officer | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | |
| 4 | Evaluation of the Technical drawings and details submitted and acceptance of the same by TPO or the empanelled professionals or the designated officers, as the case may be, if the documents submitted are accepted by the CEO and also verification of compliance of conditions incorporated for obtaining NOCs from different departments. | A | 2 | 2 | 2 | 3 | 3 | 3 | 4 | 4 | 4 | 6 | 6 | 6 | 5 | 5 | 5 | |
| 4 | Evaluation of the Technical drawings and details submitted and acceptance of the same by TPO or the empanelled professionals or the designated officers, as the case may be, if the documents submitted are accepted by the CEO and also verification of compliance of conditions incorporated for obtaining NOCs from different departments. | C | 3 | 3 | 3 | 4 | 4 | 4 | 6 | 6 | 6 | 9 | 9 | 9 | 8 | 8 | 8 | |
| 5 | Submission of evaluation report to the CEO, with or without changes | A | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | |
| 5 | Submission of evaluation report to the CEO, with or without changes | C | 3 | 3 | 3 | 4 | 4 | 4 | 6 | 6 | 6 | 9 | 9 | 9 | 8 | 8 | 8 | |
| 6 | CEO to approve the technical drawings and details submitted, with the changes recommended by the TPO or the empanelled professional | A | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | |
| 6 | CEO to approve the technical drawings and details submitted, with the changes recommended by the TPO or the empanelled professional | C | 4 | 4 | 4 | 5 | 5 | 5 | 7 | 7 | 7 | 10 | 10 | 10 | 9 | 9 | 9 | |
| Sl.No | Description of Standard Activities or the designated officer, as the case may be. | Description of Additional Activities | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) |
| Sl.No | Description of Standard Activities or the designated officer, as the case may be. | Description of Additional Activities | ** | B1 | B1 | B1 | B2 | B2 | B2 | B3 | B3 | B3 | B4 | B4 | B4 | B5 | B5 | B5 |
| Sl.No | Description of Standard Activities or the designated officer, as the case may be. | Description of Additional Activities | ** | a* | b* | c* | a* | b* | c* | a* | b* | c* | a* | b* | c* | a* | b* | c* |
| Sl.No | Description of Standard Activities or the designated officer, as the case may be. | Description of Additional Activities | ||||||||||||||||
| 7 | Issuing endorsement by TPO, in case of discrepancy in the Technical details submitted | A | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | |
| 8 | Applicant to rectify the defects and resubmit the technical drawings and details and acceptance of the same by the TPO or the empanelled professional or the designated officer, as the case may be. | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | ||
| 9 | CEO to forward application, technical drawings and details submitted for NOCs, to the concerned departments, along with required fees paid by the applicant, if the technical drawings and details submitted by the applicant is approved by the CEO. | A | - | - | - | - | - | - | - | - | - | 1 | 1 | 1 | 1 | 1 | 1 | |
| 9 | CEO to forward application, technical drawings and details submitted for NOCs, to the concerned departments, along with required fees paid by the applicant, if the technical drawings and details submitted by the applicant is approved by the CEO. | C | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | |
| 10 | CEO to forward the required details to the selected empanelled professional for site inspection to verify the site plan submitted. | A | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | |
| 10 | CEO to forward the required details to the selected empanelled professional for site inspection to verify the site plan submitted. | C | 5 | 5 | 5 | 6 | 6 | 6 | 8 | 8 | 8 | 11 | 11 | 11 | 10 | 10 | 10 | |
| 11 | Site inspection and submission of Inspection report by empanelled professional, to the CEO, | A | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | |
| 11 | Site inspection and submission of Inspection report by empanelled professional, to the CEO, | C | 7 | 7 | 7 | 8 | 8 | 8 | 10 | 10 | 10 | 13 | 13 | 13 | 12 | 12 | 12 | |
| Sl.No | Description of Standard Activities with or without noting of discrepancy. | Description of Additional Activities | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) | Timelines for different types of approvals for different types of buildings (based on height) |
| Sl.No | Description of Standard Activities with or without noting of discrepancy. | Description of Additional Activities | ** | B1 | B1 | B1 | B2 | B2 | B2 | B3 | B3 | B3 | B4 | B4 | B4 | B5 | B5 | B5 |
| Sl.No | Description of Standard Activities with or without noting of discrepancy. | Description of Additional Activities | ** | a* | b* | c* | a* | b* | c* | a* | b* | c* | a* | b* | c* | a* | b* | c* |
| Sl.No | Description of Standard Activities with or without noting of discrepancy. | Description of Additional Activities | ||||||||||||||||
| 12 | Approval of Site Inspection Report by the CEO, by accepting or rejecting the noting of discrepancy, if any. | A | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | |
| 12 | Approval of Site Inspection Report by the CEO, by accepting or rejecting the noting of discrepancy, if any. | C | 8 | 8 | 8 | 9 | 9 | 9 | 11 | 11 | 11 | 14 | 14 | 14 | 13 | 13 | 13 | |
| 13 | Issuing endorsement in case of discrepancy in the Site Inspection Report accepted by the CEO | A | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | |
| 14 | Applicant to rectify the defects and resubmit the respective drawing and detail as per the endorsement and acceptance of the same by the TPO | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | ||
| 15 | Receipt of all required NOCs from the respective departments. | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | ||
| 16 | On receipt of all the required NOCs and approval of site inspection report by the CEO, the CEO to sanction the building licence and forward the challan for payment of fees, to the applicant. | A | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | |
| 16 | On receipt of all the required NOCs and approval of site inspection report by the CEO, the CEO to sanction the building licence and forward the challan for payment of fees, to the applicant. | C | 9 | 9 | 9 | 10 | 10 | 10 | 12 | 12 | 12 | 15 | 15 | 15 | 14 | 14 | 14 | |
| 17 | Payment of Fees by land owner / promoter for the NOCs and building licence. | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | - | |
| 18 | CEO to issue building licence and the NOCs received from the concerned departments. | A | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 2 | 2 | 2 | 2 | 2 | 2 | |
| 18 | CEO to issue building licence and the NOCs received from the concerned departments. | C | 10 | 10 | 10 | 11 | 11 | 11 | 13 | 13 | 13 | 17 | 17 | 17 | 16 | 16 | 16 |
a* - new construction b* - addition / Alteration c* - revised licence ** A – Timeline for each activity C- Cumulative timeline upto that activity
Note: Additional time of 15 days shall be provided to the Environment cell to issue Clearance for projects falling in the category of Table 15.2 and 15.3