7.1.7.1 Supervision.- All construction except load bearing buildings up to 3 storeys shall be carried out under supervision of the Construction Engineer on Record (CER) or Construction Management Agency on Record (CMAR) for various seismic zones.
7.1.7.2 Certification of structural safety in construction.- CMR shall give a certificate of structural safety of construction as per Performa given in Form- XVA at the time of completion, stating that the building is structurally safe and the construction is in accordance with the specified designs and drawings provided by SER (as per Clause 3.17).
7.1.8Quality control and inspection.- All material and workmanship shall be of good quality conforming generally to accepted standards of Public Works Department and Indian standard specification and codes as included in Part-V Building Materials and Part-VII Construction management, practices and safety of National Building Code of India.
7.1.8.1 Inspection.- All the construction for high-rise buildings higher than seven storeys, public buildings and special structures shall be carried out under quality inspection program prepared and implemented under the Building Quality Auditor (BQA) in seismic zones IV and V (as notified by the Government).
7.1.8.2 Certification of quality of construction.- Empanelled Quality Auditor on Record (QAR) shall give a certificate of quality control as per Performa given in Form- XVI
Quality Inspection Program to be carried on the site shall be worked out by BQA in consultation with the owner, builder and CMR.
Note: Clause 7.1.7 and 7.1.8 shall not be applicable for Government buildings that are designed and constructed under the supervision of in-house architects/engineers.
7.1.9Control of signage and outdoor display structures, cell phone towers and telephone Towers.- Following provisions shall apply for telecommunication infrastructure
(a) Location: The Telecommunication Infrastructure shall be either placed on the building roof tops or on the ground or open space within the premises subject to other regulations;
(b) Type of structure;
(i). Steel fabricated tower or antennae on M.S. pole;
(ii). Pre-fabricated shelters of fibre glass or P.V.C. on the building roof top /terrace for equipment;
(iii). Masonry Structure/ Shelter on the ground for equipment; and
(iv). D.G. set with sound proof cover to reduce the noise level.
(c) Requirement:
(i). Every applicant has to obtain/ procure the necessary permission from the ‘Standing Advisory Committee on Radio Frequency Allocation’ (SACFA)issued by Ministry of Telecommunications;
(ii).Every applicant will have to produce the structural safety and stability certificate for the tower as well as the building from the Structural Engineer on Record (SER) which shall be the liability of both owner and SER.; and
(iii). Applicant has to produce / submit plans of structure to be erected
(d). Projection: No Pager and/or Telephone Tower shall project beyond the existing building line of the building on which it is erected in any direction.
7.2 Inspection.- The general requirement for inspection and certification of the development shall be as prescribed in Clause no.3.10.6
7.2.1 Maintenance of Buildings.- In case of building older than fifty years, it shall be the duty of the owner of a building, to get his building inspected by a Structural Engineer on Record (SER) within a year from the date of coming into force of these regulations. The Structural Inspection Report (Form No.16, of the MHA Expert Committee Report) shall be produced by the Owner to the Appropriate Authority. If any action, for ensuring the structural safety and stability of the building is to be taken, as recommended by SER, it shall be completed within five years. For other buildings, the owner shall get his building inspected after the age of building has crossed forty years. The procedure shall be followed as per above regulation.
7.2.2Protective Measures in Natural Hazard Prone areas.- In natural hazard, prone areas identified under the land use Zonal Regulations, structures buildings and installations which cannot be avoided, protective measures for such construction/development should be properly safeguarded based on the suggestion given in the Report of the MHA Expert Committee - Volume I.
7.3 Registration.- Registration of the required Professionals on Record (for drawings and supervision) has to be done as per the provisions of Appendix I and Appendix IA
7.4 Appointment of Professionals on Record.- The owner/promoter shall appoint the required Professionals on Record (for drawings and supervision) as per Appendix IA for the building licence and construction of the respective building.
7.5 Alternative Materials, Methods of Design and Construction and Tests.- The provision of the Bye-Laws is not intended to prevent the use of any material or method of design or construction not specifically prescribed by the bye-law provided any such alternative has been approved. The building materials approved by B.I.S. or any statutory body will form part of the approved building material and technology as part of the Bye-Laws.
The Authority shall promote and encourage use of Pre-fabricated factory-made building components for medium to large scale projects that have significant impact. The use of ready mix concrete (RMC) shall also be encouraged for in-situ concrete constructions.
Clause 11.2.6 may be referred for further aspects of Sustainability and incentivized promotion of alternative materials, methods in construction.