16.1 Project Listing
To ensure the implementation of Master Plan proposals, the proposals have been projectised. The clear definition of projects, responsible agencies and time schedule shall help line departments visualise long term requirements and prioritise their actions in their budgets and financial resources taking into account the projects identified by Master Plan. Projectisation would also help in better coordination among various line agencies and concerned stakeholders. Broadly following are the Projects and Programmes identified by Master Plan for implementation:
A. Road Development Plan: This includes following components
-
Demarcation of Master Plan Roads (18m above only) on Ground
-
Upgradation/ Widening of Existing Roads
-
Development of New Links
-
Junction Improvement Programme and Development of Flyovers/ Railway Bridges
-
Preparation of Parking plans for Streets/ Areas
B. Public Transport Network Development: This includes following components
-
Development of Commuter Rail Service
-
Development of Metro Network
-
Development of LRT/Mono Rail/ BRTS
-
Development of Intermodal Interchanges
-
Development ISBTs
-
Development of Bus Stations/ Terminals
C. Development of Logistic Facilities: This includes following components
-
Demarcation of Land for Logistic Facilities
-
Development of Logistic Hubs/ Truck Terminals
D. Rejuvenation of Lakes and Streams: This includes following components
-
Prioritise Lakes for Rejuvenation
-
Demarcation of Lakes Extent
AUTHORITY ★
-
Demarcation of Primary, Secondary & Tertiary Drains (which are not existing on ground, missing links only)
-
Preparation of Lake Rejuvenation Plans and Lake Area Development Plan
-
Preparation of Stream Development Plans
-
Implementation of Plans and Project for Lake & Stream Rejuvenation
E. Green Development Plan: This includes following components
-
Demarcation of Regional Parks
-
Demarcation of Other Parks
-
Land Acquisition of Regional & Other Parks
-
Development of Parks and Open Spaces (Regional Parks & Other Parks)
-
Avenue Plantation (Master Plan Roads)
-
NGT Buffer Area Development
-
Block Plantation in Villages / Forest Areas
-
Development of Sports Complex’s
F. Redevelopment/ Upgradation/ Development Plans: This includes following components
-
Preparation of Industrial Area/ Estates Redevelopment Plans
-
Preparation of Area Redevelopment Plans/ Upgradation of Urban Villages
-
Preparation of Slum Redevelopment Plans
-
Preparation of Village Development Plans
G. Heritage Area Protection and Conservation Scheme: This includes following components
-
Grading and Listing of Heritage Buildings
-
Preparation of Heritage Master Plan for Bengaluru
H. Development of Social Infrastructure: This includes following components
- Development of Crematoriums/ Graveyards
a. Land Identification and Demarcation of Land
b. Development of Facility
- Development of Fire Stations
a. Land Identification and Demarcation of Land
AUTHORITY ★
b. Development of Facility
- Development Night Shelters
a. Land Identification and Demarcation of Land
b. Development of Facility
4. Street Vending
a. Preparation of Street Vending Plan
b. Declaration of Street Vending Zones and Streets
I. Development of Physical Infrastructure: This includes following components Water Supply & Sewerage
-
Finalisation of Water Source and development of Trunk Pipeline to BMA
-
Development of Water Supply and Sewerage Network for BBMP
-
Preparation of Water Supply and Sewage Network Plan for areas outside BBMP
-
Development of Water Supply and Sewerage Network for Areas outside BBMP
Solid Waste Management
- Demarcation of Land and Development of SWM facilities
a. Dry Waste Collection Centre
b. Organic Waste Collection Center (OWCC)
c. Aggregators (AGGR)
d. Bio-Methanation Units (BMU)
e. Coconut waste Processing Unit (CPU)
f. Integrated Waste Processing unit (IWPU)
g. Central processing unit
h. Leaf litter
i. Landfill
Power Supply
- Demarcation of Land and Development of Sub-station (220kv only)
J. Disaster & Hazard Management: This includes following components
-
Preparation of Disaster & Hazard Mitigation Plan
-
Implementation of Components and Projects of Disaster & Hazard Mitigation Plan
BANGALOE AUTHORITY ★
K. Town Planning Scheme / Development Schemes: This includes following components
-
Prioritise Area for TPS / DS/ SDZ
-
Identity extent and declare intention of prepare TPS / DS (2/3 Schemes)
-
Planning & Implementation of Scheme
16.2 Phasing and Responsible Agencies
Table 16-1 lists the projects/ actions proposed by Master Plan, the responsible agencies and phasing of projects (time schedule).
★
| Phasing of Master Plan Programme & Projects | |||||||
| Main Programme/ Project/ Action | Agency Responsible | Phase 1 [2018-24] | Phase 2 [2025-31] | ||||
| Road Development Plan | |||||||
| Land Demaoncation of Master Plan Roads (18m & above roads) | BDA & BBMP | ||||||
| Land Acquisition for Master Plan Roads | BDA & BBMP | ||||||
| Development of PRR (Northern Stretch) | BDA | ||||||
| Development of ORR (Part Stretch) | BDA | ||||||
| Development of Intermediate Ring Road | BBMP | ||||||
| Development of BMR Regional Links | BDA | ||||||
| Upgradation of NH/ SH | NHAI/ PWD/ KSRDCL | ||||||
| Development of Missing Links and upgradation of Existing Links of Inner PRR | BBMP/ BDA | ||||||
| Development of Other Master Plan Roads | BBMP/ BDA/ PWD/ KSRDCL/NHAI | ||||||
| Upgradation/ Widening of Existing Roads (within BBMP) | BBMP | ||||||
| Upgradation/ Widening of Existing Roads (outside BBMP) | BDA | ||||||
| Upgradation of Village Roads | Gram Panchayath | ||||||
| Development of Railway Bridge/ Underpass | BDA/ BBMP/ PWD | ||||||
| Improvement of Major Junctions & Development of Flyovers/ Cloverleafs, Grade Seperators | BDA/ BBMP/ PWD/ KSRDCL | ||||||